project snapshot

Luxury Bedfordshire Wedding Venue

System size 190kWp peak / 150kW max active AC power
Payback period 5.5 years
Internal rate of return 18.45%
Return on investment 221.66%
First year savings £37,752
Lifetime bill savings £691,642
Annual carbon reduction 37 tonnes CO2
Lifetime carbon reduction 925 tonnes CO2

Solar PV System for Wedding Venue
the client

Luxury wedding venue

The business is a luxury wedding venue and working farm in Bedfordshire situated within the boundaries of a national scheduled monument. The venue offers a full catering operation, function rooms, bar areas, bridal suites, a traditional barn for ceremonies, and on-site accommodation.

"Given the historical nature of our site and the complexities that this presented, the team at Practical Energy Solutions were able to successfully navigate all of the administrative hurdles that we faced prior to installation. Once all of the approvals were secured, the installation itself was carried out to a high standard, and the systems are working extremely well."
Bassmead Manor Barns testimonial
Richard Squire, Owner and Director
Bassmead Manor Barns
the challenge

Rising energy costs

With no mains gas supply, the business was heating the venue and producing hot water entirely through oil-fired boilers, at a cost of around £74,000 per year in combined energy spend. Annual electricity consumption was approximately 280MWh.

Rising energy costs, combined with a genuine commitment to reducing the site's carbon footprint, led the business to explore solar PV, but the location created significant additional complexity. The site's status as a scheduled monument and designated conservation area meant any development would face scrutiny from heritage bodies.

route to a solution

Managing the planning process

Practical Energy Solutions (PES) modelled the solar PV system to maximise generation within the constraints set by the District Network Operator (DNO). The rural grid infrastructure limited maximum system output to 150kW – beyond which a new substation would have been required, adding substantial cost.

The original proposed location for the solar arrays was objected to by the planning department on heritage grounds, to protect the significance of the listed manor house and medieval moat. As a result, the arrays were relocated approximately 0.5km eastward, to an area of low-grade arable land set aside from the main farm.

Following archaeologist intervention, the mounting method was also changed from ground screws to concrete block fixings to protect any historical assets that might be present beneath the site.

PES managed the entire planning process on behalf of the client, including:

the system

Final installation

The final installation comprised:

All installation work was carefully timed to cause minimum disruption to the business. The final grid connection required only a 4-hour site power-down.

the results

Significant savings

The system locks in a levelised energy cost of 7.6p per kWh for 25+ years, protecting the business against future energy price rises.

Pre-solar Post-solar Impact
Annual energy cost £74,000 £37,000 £37,000 saved annually
Grid reliance 100% 65% 35% reduction
Cost per kWh (all consumption) 27p 13.2p 13.8p saving per kWh
Carbon emissions (electricity) 56 tonnes 19 tonnes 66% reduction in Scope 2 emissions
Carbon emissions (oil) 46.9 tonnes 0 tonnes 100% reduction in Scope 1 emissions
site emissions

ECG and wider benefits

The reduction in site emissions supports the conservation of the historical assets on the estate – a consideration that resonated strongly with the client and with the heritage bodies involved in the planning process. The installation also represents a meaningful step in the business's ESG journey, and one it can communicate directly to wedding venue clients.